Öffentlichkeitsbeteiligung im Rahmen der Planfeststellung zu Netzausbauvorhaben Durchführung
Inhalt
Begriffe im Kontext
Fachlich freigegeben am
Fachlich freigegeben durch
Are you interested in power grid expansion projects? Then you can find out more and get directly involved in various ways.
In the planning approval procedure, the public and the authorities concerned are involved in deciding on the specific, area-specific design of the expansion measures. Among other things, the actual route of the pipeline and the specific technical design are determined.
The planning approval process must be as transparent as possible. You can participate as a public interest group or association, but also as a member of the public.
You have three opportunities to formally participate in the planning approval process:
- The first important opportunity is the public application conference. This is held by the Federal Network Agency after it has received the application for plan approval. The project developers prepare the application beforehand. At the conference, the Federal Network Agency gathers information on regional conditions. Anyone who also has alternatives to the proposed route can present them at the application conference. The Federal Network Agency also receives comments on environmental and spatial compatibility. From this, it prepares a homework booklet for the project developers, the so-called investigation framework.
- The next opportunity for participation is for the authorities and the public to get involved. This takes place after the developer has completed its investigations. The Federal Network Agency publishes information on the interpretation
- on its website
- and in the local daily newspapers.
- You can submit comments as an affected private person, but also as a public interest group. Public interest groups are, for example, municipal authorities.
- After the Federal Network Agency has received and reviewed all the comments, it organizes a hearing. This is the third and last opportunity to participate in the planning approval process. At this meeting, it discusses the comments made in good time with the developer, the public interest groups and those who made them. In contrast to the application conference, you can only participate in this meeting if you have submitted a statement.
- The result of the plan approval is the final decision on the project, taking into account and weighing up all the
- public concerns (nature conservation, landscape protection, municipal planning, cultural monuments and so on)
- and private concerns (property, health).
If the Federal Network Agency is of the opinion that the planned project meets all legal requirements after a thorough examination and consideration of all the interests concerned, it issues the zoning decision.
Projects designated as transnational or cross-border for the construction and operation of transnational or cross-border power lines must first undergo federal sectoral planning and then plan approval.
No documents are required to submit comments. However, it may be helpful if you enclose appropriate maps or other documents. This makes the statement easier for the Federal Network Agency to understand.
Comments may be submitted by all private individuals, associations or public bodies whose interests are affected.
- As a first step, the Federal Network Agency holds a public application conference. To this end, it invites associations and public interest groups. In principle, however, participation is open to all interested parties. After the application conference, the Federal Network Agency defines the scope of the investigation.
- The hearing procedure then starts with the display and publication of the documents. Here, public bodies, private individuals and environmental associations whose interests are affected by the project have the opportunity to comment. You can preferably use the online form to submit your comments to the Federal Network Agency.
- A hearing will then be held with those entitled to participate.
- Deadline for citizens and associations to submit comments: 1 month
- Deadline for public bodies: usually 8 weeks
- Administrative court action against the approval decision for the respective expansion measure (Federal Administrative Court)
- Public participation in the context of plan approval for grid expansion projects Implementation
- Current information on power grid expansion projects
- Participation of authorities and the public
- Submission of comments
- Online form
- Registration for application conferences
- Registration for hearing dates
- Objection period begins with the publication of the documents and ends 1 month after the end of the publication period.
- Responsible: Federal Network Agency (BNetzA)
- Forms: yes
- Online procedure possible: yes
- Written form required: yes
- Personal appearance required: no