Verlängerung der Baugenehmigung für die Errichtung einer Anlage beantragen
Inhalt
Begriffe im Kontext
- Kauf und Verkauf von Immobilien, einschließlich aller Bedingungen und Pflichten im Zusammenhang mit der Besteuerung, dem Eigentum oder der Nutzung von Immobilien (auch als Zweitwohnsitz)
Fachlich freigegeben am
Fachlich freigegeben durch
You can apply for an extension of the building permit for up to two years at a time if you have a valid building permit for the construction of an installation for your building project.
The building permit expires if you do not start building work within three years of the permit being granted or if building work has been interrupted for one year.
The deadline can be extended by up to two years in each case with a written application if the legal requirements have not changed in the meantime and the application has been received by the lower building supervisory authority before the deadline expires. The extension of the building permit is subject to a fee.
- Valid building permit
- Application before expiry of the extension period of three years since the building permit was issued
- the legal requirements have not changed in the meantime
At least EUR 100.
The fee is to be calculated proportionately according to the extent to which the building permit is anticipated by the preliminary decision.
The respective local authorities can set fees by statute. Please contact the building supervisory authority responsible for you.
- You make the application informally and submit it to the responsible building supervisory authority together with any necessary documents.
- The building supervisory authority will review your application.
- If the factual and legal situation has not changed, there is nothing to prevent an extension of up to two years. The extension is subject to a fee.
- Application for extension during the term of the building permit, which is three years.
- The building permit can be extended by up to two years at a time.
An appeal may be lodged against the authority's decision within one month of notification.
- Construction of facilities Extension of the permit
- Can be extended for up to two years at a time
- No change to the legal requirements
- Application must be received before the deadline expires
- The lower building supervisory authority (building supervisory authorities of the administrative districts, independent cities and special status cities)
Please contact the lower building supervisory authority of your district, independent city or special status city.