Immissionsschutz - Messbericht über Einzelmessungen von Luftschadstoffen bei Anlagen gemäß Genehmigungsbescheid einreichen
Inhalt
Begriffe im Kontext
Fachlich freigegeben am
Fachlich freigegeben durch
- § 26 Messungen aus besonderem Anlass
- § 28 Erstmalige und wiederkehrende Messungen bei genehmigungsbedürftigen Anlagen
- § 21 Inhalt des Genehmigungsbescheides
If you operate or wish to operate certain industrial or commercial facilities that require a permit, the authorities may stipulate in the permit that you must have the pollutant emissions checked at regular intervals by means of individual measurements.
The measurements must be carried out by a notified body (measuring centre) in accordance with § 29b of the Federal Immission Control Act (BImSchG). You must draw up a measurement report on the results and submit it to the responsible immission control authority.
Complete measurement report in accordance with Annex A of Guideline VDI 4220 Sheet 2 (November 2018 edition) with information on, among other things
- Measurement results,
- measurement methods used,
- Operating conditions that are important for the assessment of the measurement results.
You have received a notice of approval for an industrial or commercial facility that requires authorisation.
- Individual measurements are specified by the authorities in the authorisation notice for your installation.
- You contact a notified body (measuring centre) in accordance with Section 29b of the Federal Immission Control Act.
- The exact measurement planning (measurement date, air pollutants to be measured, operating conditions of the installation to be taken into account, ...) must be agreed between you, the measuring centre and the responsible immission control authority.
- The measuring centre determines the emission values on the measurement date.
- Once the measurement has been completed, you will receive a measurement report from the measuring centre, which must be submitted to the responsible immission control authority.
- Measurements must be carried out within the deadlines specified in the authorisation notice.
- The associated measurement reports must be submitted to the competent authority within the deadlines specified in the approval notice.
Please ensure that you submit the measurement report to the immission control authority responsible for your installation.