Immissionsschutz: Störfallrelevante Errichtung und Betrieb oder Änderung von nicht genehmigungsbedürftigen Anlagen melden
Inhalt
Begriffe im Kontext
- Erlangung von Lizenzen, Genehmigungen oder Zulassungen im Hinblick auf die Gründung und Führung eines Unternehmens
Fachlich freigegeben am
Fachlich freigegeben durch
- § Section 23a (1) sentence 1 of the Federal Immission Control Act (BImSchG)
- Fourth Ordinance on the Implementation of the Federal Immission Control Act (4th BImSchV)
- Twelfth Ordinance on the Implementation of the Federal Immission Control Act (12th BImSchV)
- Ninth Ordinance on the Implementation of the Federal Immission Control Act (9th BImSchV)
- Immission Control State Ordinance (ImmSchZustLVO M-V)
- Immission Control Cost Ordinance (ImmSchKostVO M-V)
If you are planning an incident-relevant construction and operation or an incident-relevant change to an installation that does not require a permit and is an operating area or part of an operating area, you must register this.
Do you operate an installation that does not require a permit under immission control legislation, which is an operating area or part of an operating area, and are you planning an interference-relevant change to it?
Or are you planning an incident-relevant construction and operation of an installation that does not require a permit and is an operating area or part of an operating area?
These projects can lead to a significant increase in risk from the installation as a result of the construction or modification or other immission law requirements can no longer be guaranteed.
The immission control authorities must therefore be informed of these changes so that the requirements under immission law can be checked. To do this, you must register your project with the responsible authority before it is carried out. The notification can be made in writing or electronically.
- Required drawings, plans, expert opinions
- explanations and
- other documents (if necessary, ask the competent authority)
An accident-relevant construction and operation as well as accident-relevant changesnstallation must be registered with the competent authority if:
- the installation is not subject to licensing and is either an operating area or part of an operating area,
- an incident-relevant construction and operation or incident-relevant modification is planned and
- a permit has not already been applied for the construction and operation of an installation relevant to an incident or the modification of an installation not requiring a permit.
An incident-relevantlicensing procedure for an installation not subject to licensing is required and must be applied for if:
- the plant falls below the appropriate safety distance for the first time,
- the distance is further reduced or
- a significant increase in risk is triggered.
Fees are charged for the official act. The amount is primarily based on the installation costs of the facility or the administrative costs. Further details are regulated by the Immission Control Costs Ordinance M-V.
- You notify the competent authority of the construction or modification of the installation that does not require a permit before it is commissioned or before your project is implemented.
- You can do this using the EliA service or in writing. You enclose the necessary documents with the notification.
- The competent authority will confirm receipt of the notification and the enclosed documents. If necessary, the authority will request further and/or additional documents.
- No later than two months after receipt of the notification and the complete documents, the competent authority will inform you whether or not your project requires approval.
- If the competent authority informs you that no approval procedure is required, you as the operator or owner of the project can carry out the construction and operation or modification immediately after the authority's notification.
- However, if the authority comes to the conclusion that your project requires a permit, you must then apply for a permit for an accident-relevant construction oraccident-relevantrelevant modification.
- Incident-relevant construction and operation or incident-relevant modification of an installation not subject to licensing; receipt
- Notification of an installation relevant to a major incident and the operation or modification relevant to a major incident of an installation that does not require a permit and is an operating area or part of an operating area
- if the installation is an operating area or part of an operating area
- a permit in accordance with § 23b BImSchG is not applied for
- Notification ELiA or in writing
Forms available: Yes
Written form required: Yes
Informal application possible: No
Personal appearance necessary: No