Immissionsschutz: Genehmigung für die Errichtung von Anlagen mit vorzeitigem Beginn beantragen
Inhalt
Begriffe im Kontext
- Erlangung von Lizenzen, Genehmigungen oder Zulassungen im Hinblick auf die Gründung und Führung eines Unternehmens
Fachlich freigegeben am
Fachlich freigegeben durch
- § Section 8a of the Federal Immission Control Act (BImSchG)
- § Section 10 of the Federal Immission Control Act (BImSchG)
- Fourth Ordinance on the Implementation of the Federal Immission Control Act (Ordinance on Installations Requiring a Permit - 4. BImSchV) Annex 1
- 9th Ordinance on the Implementation of the Federal Immission Control Act (9th BImSchV)
- Environmental Impact Assessment Act
- State ordinance on the responsibility of the immission control authorities
- Immission Control Cost Ordinance (ImmSchKostVO M-V)
Have you applied for a permit for an installation that requires approval? Then you can also apply to start construction of the system ahead of schedule.
Have you applied for a permit for an installation that requires approval? If so, you can also apply to the competent authority for permission to begin construction of the facility ahead of schedule.
The competent authority can revoke the permit at any time. In addition, the approval may be subject to conditions or be granted conditionally if you still have to meet certain requirements. The conditions are intended to ensure that the installation can be dismantled if it is not approved. To this end, the competent authority may require you to provide security. Collateral can be, for example, the deposit of money or securities as well as guarantees.
- Application for early construction of an installation requiring approval
- Required drawings, plans, expert opinions
- Explanations of the installation
- Other documents (if necessary, ask the competent authority)
- The competent authority must be able to adequately assess the impact of the planned installation from the application and the required documents.
- Your application must demonstrate a legitimate interest in the early start.
- As the applicant, you must undertake to compensate for all damage caused by the premature construction up to the time of the decision and, if the project is not approved, to restore it to its previous state.
Fees are charged for the official act. The amount is primarily based on the installation costs of the facility or the administrative costs. Further details are regulated by the Immission Control Costs Ordinance M-V.
If you wish to apply to the competent authority for a partial permit for an installation requiring a permit, you must first submit the application documents in full.
You can do this in writing or electronically. The competent authority will confirm receipt of the application in writing or electronically, check it for completeness and involve other specialist authorities if necessary.
If necessary, the authority will request further documents.
6 months for the formal procedure
3 months for the simplified procedure
If you wish to obtain approval for significant changes to an installation requiring approval, the competent authority can also provisionally approve the operation of the installation if the change serves to ensure the lawful construction or operation of the installation.
- Objection
- Further information on how to lodge an appeal can be found in the notification.
- Complaint
- Approval for the early construction of an installation requiring a permit in accordance with the BImSchG
- In ongoing proceedings for the granting of a permit, the approval authority may, upon application, provisionally allow construction to begin, including the measures required to test the operational capability of the installation
- Responsible: State Offices for Agriculture and the Environment (StÄLU)