Zulassung des vorzeitigen Beginns einer genehmigungsbedürftigen Anlage beantragen
Inhalt
Begriffe im Kontext
- Erlangung von Lizenzen, Genehmigungen oder Zulassungen im Hinblick auf die Gründung und Führung eines Unternehmens
Fachlich freigegeben am
Fachlich freigegeben durch
As part of an application for a permit under the Federal Immission Control Act (Bundesimmissionsschutzgesetz), you can submit an application for approval of an early start. In order to accelerate the planned project, the construction of the plant can also be permitted prior to the granting of the permit up to the testing of the operational capability in accordance with Section 8a (1) of the Federal Immission Control Act (BImSchG). This may involve the approval of individual erection steps or even the entire erection, whereby the approval of all erection measures is only permissible in exceptional cases.
Specific information on the required documents is not possible due to the large number. Information on this can be obtained from the responsible office.
- A decision in favor of your application can be expected,
- There is a public interest or you have a legitimate interest in the early start, and
- You agree to compensate for all damages caused by the construction of the facility until the decision is made and, if the project is not approved, to restore it to its previous condition.
The fees are based on No. 2.1.4 of the Thuringian Administrative Cost Regulations for the Business Division of the Ministry for the Environment, Energy and Nature Conservation (ThürVwKostOMUEN) of 14.10.2011.
Concrete details on the procedure are not possible due to the diversity. More information is available from the responsible office.
- Appeal
- For more information on how to file an appeal, see the notice of your application.
- Early construction of a plant requiring a permit in accordance with BImSchG Permit
- In a procedure for the granting of a permit, the licensing authority shall, upon application, provisionally permit construction, including the measures required for testing the operational reliability of the installation, to commence prior to the granting of the permit if
- a decision in favor of the applicant can be expected,
- there is a public interest or a justified interest of the applicant in the early start, and
- the applicant undertakes to compensate for all damage caused by the construction of the facility up to the time of the decision and, if the project is not approved, to restore it to its previous condition.
- Responsible: immission control licensing authorities of the federal states (TLUBN or counties and independent cities).
Please contact the immission control authorities in Thuringia: Thuringian State Office for the Environment, Mining and Nature Conservation (TLUBN) or the district and independent cities.
Forms available: Yes
Written form required: Yes
Informal application possible: No
Personal appearance required: No
Online services available: Yes