Gewährleistung der Betriebssicherheit - Erlaubnis zur Errichtung und zum Betrieb von Dampfkesselanlagen beantragen
Inhalt
Begriffe im Kontext
- Gesundheits- und Sicherheitsvorschriften im Zusammenhang mit verschiedenen Arten von Tätigkeiten, einschließlich der Risikovermeidung, Information und Ausbildung
Fachlich freigegeben am
Fachlich freigegeben durch
If you want to build, operate or make certain modifications to a Category IV steam boiler plant, you must apply for a permit from the competent authority.
Steam boiler systems of the so-called category IV are heated pressure equipment at risk of overheating for the production of steam or hot water with a temperature of more than 110 degrees Celsius. These are systems that need to be monitored.
You will need a permit from the relevant authority if you are using a Category IV steam boiler installation.
- want to build and put into operation, or
- want to change the design or mode of operation in such a way that the safety of the system is affected.
Permission can be granted to you subject to the following restrictions:
- limited
- temporary
- under conditions, or
- with conditions.
If the installation requiring a permit is part of an installation requiring a permit, no separate permit will be issued. The permit includes the permission.
Informal application with the following information:
- Last name, first name, company name
- Address of the applicant
- Contact information (e-mail, telephone number, fax)
- Type of permission:
- Construction and operation
- modification and operation, or
- Partial permission
- Indication of the place of operation
Documents to be able to assess the plant:
- Subject matter of the application
- Description of the plant
- Description of the plant technology and interaction with other plants
- Piping and instrumentation flow diagram (P&ID diagram)
- Description of boiler installation room (ventilation, pressure relief surfaces)
- Description of the mode of operation
- Description of the exhaust system
- Lay-out
- Site plan
- Floor plan or technical plan
- Description Assembly
- Description of the conformity assessment procedure
- Information on fire protection
- Calculation of production costs
- Supplements of the TÜV Verband e.V. for boiler approval procedures
- Other installations
- Test report of an approved inspection body (ZÜS)
- The test report must confirm that the system can be operated safely if the above measures are observed.
- file number and indication of the approval authority of a building permit that has already been issued, or
- to the approval authority in the case of a building permit that has yet to be applied for or has already been applied for
- The plant for which you are applying for the permit must be an installation requiring a permit.
- They must construct and operate state-of-the-art steam boiler systems.
- Your documentation must be complete, plausible and meaningful.
- The test report of the approved inspection body (ZÜS) must confirm that the requested installation can be operated safely if the measures specified in the documents, including the tests, are complied with.
- Submit the application for permission for the installation requiring monitoring to the competent authority with the necessary documents, including the test report of the approved inspection body (ZÜS).
- If there is a permit requirement under the Federal Immission Control Act, you will receive the application documents back, as a permit under the Industrial Safety Ordinance will then be checked as part of the necessary permit under the Federal Immission Control Act.
- The competent authority shall take its decision after examination and shall inform you thereof.
The permit expires if:
- you have not started the construction of the installation within two years of the permit being granted,
- you have interrupted the construction of the installation for two years or more, or
- You have not operated the system for a period of three years.
For important reasons, you can apply to the licensing authority for an extension of the deadlines.
The publication (LV 49) contains a list of the required application documents for steam boiler plants under Annex 1.
The publication (LV 49) contains a list of the required application documents for steam boiler plants under Annex 1.
Contradiction:
- You may appeal against the decision within one month of notification.
- You must submit the objection to the competent authority in writing or for a record.
- In Rhineland-Palatinate, objections can also be filed in electronic form.
- Construction and operation of a plant requiring monitoring in accordance with the Industrial Safety Ordinance Approval of steam boiler systems
- Anyone wishing to construct or operate a category IV steam boiler system or to make changes to the design or mode of operation requires a permit.
- Category IV steam boiler installations include heated pressure equipment at risk of overheating for the production of steam or hot water at a temperature of more than 110 degrees Celsius.
- These are "systems requiring monitoring" that must be assembled, installed and operated according to the state of the art.
- The permit can:
- granted subject to conditions,
- limited
- for a limited period of time and
- be subject to conditions.
- Application: informally in writing or electronically
- An application for partial permission is possible.
- responsible: Occupational health and safety authority or trade supervisory authority
- in Rhineland-Palatinate: Regional offices of the Labour Inspectorate of the Structure and Approval Directorate North (SGD North) or South (SGD South)
The competent authorities in Rhineland-Palatinate are the Labour Supervision Departments of the Structural and Licensing Authorities North and South.
Regional Offices Trade Inspectorate of the Structure and Approval Directorate North (SGD North) or South (SGD South)
Forms available: No
Written form required: Yes
Informal application possible: Yes
Personal appearance required: No
Online services available: No