Bauvorhaben; Anzeige des Baubeginns

Bayern 99012081261000, 99012081261002, 99012081261001 Typ 4

Inhalt

Leistungsschlüssel

99012081261000, 99012081261002, 99012081261001

Leistungsbezeichnung

nicht vorhanden

Leistungsbezeichnung II

Construction project; notification of the start of construction

Leistungstypisierung

Typ 4

Begriffe im Kontext

nicht vorhanden

Leistungstyp

nicht vorhanden

SDG Informationsbereiche

nicht vorhanden

Lagen Portalverbund

nicht vorhanden

Einheitlicher Ansprechpartner

nicht vorhanden

Fachlich freigegeben am

18.03.2025

Fachlich freigegeben durch

Bayerisches Staatsministerium für Wohnen, Bau und Verkehr (Bavarian State Ministry of Housing, Building and Transport)

Teaser

You must notify the start of construction in advance. This applies to the start of execution of projects requiring approval and the resumption of construction work after an interruption of more than 6 months.

Volltext

The notification of the start of construction is not an application. You only need to inform the lower building supervisory authority of the imminent start of construction.

The notification of the start of construction is intended to give the lower building supervisory authority sufficient time to prepare construction monitoring measures and to check whether the period of validity of the building permit has expired.

Consequences of non-notification

If you deliberately or negligently fail to notify the start of construction at least one week before the start of construction, you are committing an administrative offense. You can be fined up to EUR 500,000 for this. In addition, the lower building supervisory authority can order the suspension of construction.

Erforderliche Unterlagen

  • If applicable, certificate of stability I (for form see "Forms")

    The necessity depends on the project.

  • Fire protection certificate I, if applicable (for form see "Forms")

    The necessity depends on the project.

  • if applicable, declaration of compliance with the catalogue of criteria (for form, see "Forms")

    The necessity depends on the project.

    If the building application is submitted digitally, the structural engineer can also submit the declaration digitally using the online wizard (see service "Building project; online submission of the declaration of compliance with the catalogue of criteria" under "Related topics").

  • If applicable, designation of the person responsible for the construction work (for form, see "Forms")

    The necessity depends on the project.

    If the building application is submitted digitally, the structural engineer can also submit the declaration digitally using the online wizard (see service "Building project; online submission of the declaration of compliance with the catalogue of criteria" under "Related topics").

Voraussetzungen

You must notify the start of construction if:

  • you start carrying out a construction project that requires approval,
  • you resume construction work after an interruption of more than 6 months or
  • you remove an installation subject to notification.

This also applies to a project covered by a partial building permit and to projects that do not require a permit.

Kosten

none

Verfahrensablauf

Written submission

  • Submit the completed and signed "Construction start notification" form with the required attachments to the lower building supervisory authority (district offices, independent cities, large district towns and certain larger municipalities).
  • Verbal notification is not sufficient.
  • You will not receive confirmation of receipt.
  • The lower building supervisory authority will then check whether the period of validity of the building permit has not yet expired. It can also prepare construction supervision measures if necessary.

Digital submission

It is not yet possible to submit notifications of the start of construction work digitally throughout Bavaria. When a location is selected, the link to the online procedure is displayed if it is already offered.

  • The start of construction can be notified digitally to the lower building supervisory authority using the online assistant.
  • The predefined forms "Notification of start of construction" and (if required) "Designation of the structural engineer responsible for the construction work" are replaced by the queries in the online assistant.
  • Signatures are replaced by authentication using the "BayernID" user account or "My company account".
  • The remaining attachments are uploaded in electronic form (files in PDF format) in the online assistant.

Bearbeitungsdauer

nicht vorhanden

Frist

You must notify the start of construction at least one week before work begins.

Weiterführende Informationen

Hinweise

You must also report the "start of construction" if you are removing an installation and have to report this.

Rechtsbehelf

As no decision is issued by the lower building supervisory authority, you cannot lodge an appeal.

Kurztext

nicht vorhanden

Ansprechpunkt

nicht vorhanden

Zuständige Stelle

nicht vorhanden

Formulare

nicht vorhanden

Ursprungsportal