Einleiten von Abwasser in private Abwasseranlagen Genehmigung
Inhalt
<div lang="en-x-mtfrom-de">Discharge of waste water into private sewage systems permit</div>
<div lang="en-x-mtfrom-de">Apply for a permit to discharge wastewater into private wastewater plants</div>
Begriffe im Kontext
<div lang="en-x-mtfrom-de">Indirect discharger</div> (Synonym), <div lang="en-x-mtfrom-de">Rainwater</div> (Synonym), <div lang="en-x-mtfrom-de">Sewage systems</div> (Synonym), <div lang="en-x-mtfrom-de">Sewage treatment plant</div> (Synonym), <div lang="en-x-mtfrom-de">dirty water</div> (Synonym)
Fachlich freigegeben am
01.11.2023
Fachlich freigegeben durch
nicht vorhanden
If you want to discharge commercial wastewater into a private wastewater plant or sewer system, you usually need to apply for a permit in advance.
As a rule, you need a permit to discharge commercial wastewater into private wastewater systems (for example in commercial and industrial parks). You must apply for approval from the relevant authority. You must have the permit before you start discharging the wastewater.
You will be granted permission if the quality and quantity of the wastewater is suitable for being discharged into a private wastewater plant.
- You submit a written application to the responsible authority. With the application you submit further documents on the type and scope of your project. ·
- If necessary, the responsible authority will request further documents from you.
- The responsible authority will examine your application and decide whether to approve it.
- The decision of the responsible authority will be communicated to you in a written notice.
- With the notice, you may be given requirements that you must implement.
- You will receive a fee notice
- You pay the administration fees
No. However, you must have approval before you begin the initiation process. You should therefore submit the application well in advance of the intended start of your project.
The discharge permit may be associated with requirements for the pre-treatment of the wastewater and self-monitoring, which you must implement. Your discharge permit may be limited in time.
- Apply for a permit to discharge commercial wastewater into private wastewater plants
- A permit from the responsible authority is usually required to discharge commercial wastewater into a private wastewater plant