Mittelgroße Feuerungs-, Gasturbinen- und Verbrennungsmotoranlage - Anzeige der Inbetriebnahme Entgegennahme
Inhalt
<div lang="en-x-mtfrom-de">Medium-sized combustion, gas turbine and combustion engine plant - notification of commissioning receipt</div>
<div lang="en-x-mtfrom-de">Show commissioning of a medium-sized combustion, gas turbine and combustion engine plant</div>
Begriffe im Kontext
<div lang="en-x-mtfrom-de">TA Luft</div> (Synonym)
Fachlich freigegeben am
30.05.2025
Fachlich freigegeben durch
nicht vorhanden
Section 6 paragraph 1 of the Ordinance on medium-sized combustion, gas turbine and combustion engine plants (44th BImSchV)
https://www.gesetze-im-internet.de/bimschv_44/__6.html
https://www.gesetze-im-internet.de/bimschv_44/__6.html
If you're planning to commission a medium-sized combustion plant, gas turbine, or internal combustion engine, you can find out how to notify the relevant authority here.
If you plan to commission certain medium-sized combustion, gas turbine or internal combustion engine plants, you must notify this.
The notification obligation generally applies to all combustion plants, whether subject to authorisation or not, with a thermal output of at least 1 MW and less than 50 MW.
For aggregated combustion plants, you must notify the planned commissioning if the combined thermal input is more than 1 MW and less than 50 MW.
The notification obligation generally applies to all combustion plants, whether subject to authorisation or not, with a thermal output of at least 1 MW and less than 50 MW.
For aggregated combustion plants, you must notify the planned commissioning if the combined thermal input is more than 1 MW and less than 50 MW.
You would like to commission a medium-sized combustion, gas turbine or combustion engine plant.
- You submit your notification with the required information to the responsible authority in writing or electronically.
- The responsible authority will examine your notification and request further documents if necessary.
- Your notification will be registered in the asset register.
- After registration you will receive confirmation from the responsible authority.
- Submit the notification before the intended commissioning of the system.
- After receiving the notification and the complete documentation, the competent authority will register your system in the system register within 1 month.
You are committing an administrative offence if you do not submit the report, do not submit it correctly, do not submit it completely, do not submit it in the prescribed manner or do not submit it on time.
- Notification of the planned commissioning of certain medium-sized combustion, gas turbine or internal combustion engine plants
- Notification requirement for all combustion plants requiring approval and those not requiring approval with a thermal output of at least 1 MW and less than 50 MW
- Notification of planned commissioning for aggregated combustion plants with a combined thermal input of more than 1 MW and less than 50 MW