Errichtung von Anlagen Teilgenehmigung

Bremen 99012070277000 Typ 4

Inhalt

Leistungsschlüssel

99012070277000

Leistungsbezeichnung

Errichtung von Anlagen Teilgenehmigung

Leistungsbezeichnung II

Applying for a partial building permit for the construction of a system

Leistungstypisierung

Typ 4

Begriffe im Kontext

Building application (Synonym), Building permit procedure (Synonym), Building permit (Synonym)

Leistungstyp

nicht vorhanden

SDG Informationsbereiche

nicht vorhanden

Lagen Portalverbund

  • Anlagenbetrieb und -prüfung (2120100)

Einheitlicher Ansprechpartner

nicht vorhanden

Fachlich freigegeben am

24.11.2023

Fachlich freigegeben durch

nicht vorhanden

Handlungsgrundlage

Teaser

With a partial building permit, you can start construction work for the excavation pit and for individual components or construction phases before the building permit is issued. To do this, you submit an application for a partial building permit to the responsible lower building supervisory authority.

Volltext

If you have applied for planning permission and would like to start building individual sections of the building before planning permission is granted, you will need partial planning permission for this construction work. To do this, you submit an application for a partial building permit to the responsible lower building supervisory authority.

In the application, you specify which individual building components or construction phases you would like to start before the building permit is issued.

The partial building permit for the construction of a facility is subject to a fee.

Erforderliche Unterlagen

No documents required.

Voraussetzungen

You will receive a partial building permit if

  • the underlying building application is complete with regard to the construction measures applied for partial building permit and
  • the building project described is in accordance with the public law regulations to be examined in the building inspection procedure.

Kosten

The amount of the fee is based on § 1 of the Construction Costs Ordinance, tariff number 101.05.

Verfahrensablauf

You apply for a partial building permit for the construction of a facility in text form.

Submit the application, stating which building application your application for partial building permission relates to and which construction measures it covers. Attach the required building documents. Submit the application documents to the responsible lower building supervisory authority.

The lower building supervisory authority will review your application and involve those bodies whose involvement or consultation is required for the decision on the partial building permit or without whose opinion the suitability of the application for approval cannot be assessed. You will then receive the decision on your application.

The partial building permit is subject to a fee. You will receive a notification of fees. If necessary, the lower building supervisory authority will ask you to make an advance fee payment after you have submitted your application.

Bearbeitungsdauer

The lower building supervisory authority should decide on the application within twelve weeks after the completeness of the application has been confirmed in accordance with Section 69 (3) of the Bremen State Building Code.

Frist

There is no application deadline in the regular partial building permit procedure. The partial building permit expires if work on the project has not begun within three years of it being granted or if work has been interrupted for more than one year. The application can be extended once by two years within the period of validity. If a partial building permit has been granted, the lower building supervisory authority must be notified at least one week before the start of construction work.

Weiterführende Informationen

Hinweise

If you have the partial building permit, you must notify the competent lower building supervisory authority of the start of the construction work at least one week before the start of the construction work by submitting the construction start notification in accordance with § 74 sentence 2 of the Bremen State Building Regulations.