Portal für Verwaltung und Digitalisierungspartner. Feedback senden

Anzeige des Bauzustands Entgegennahme

Bremen 99012082261000 Typ 4

Inhalt

Leistungsschlüssel

99012082261000

Leistungsbezeichnung

Anzeige des Bauzustands Entgegennahme

Leistungsbezeichnung II

Show state of construction

Leistungstypisierung

Typ 4

Begriffe im Kontext

§ 81 BremLBO (Synonym)

Leistungstyp

nicht vorhanden

SDG Informationsbereiche

nicht vorhanden

Lagen Portalverbund

  • Bauplanung (2050400)

Einheitlicher Ansprechpartner

nicht vorhanden

Fachlich freigegeben am

20.03.2025

Fachlich freigegeben durch

nicht vorhanden

Handlungsgrundlage

Teaser

At the request of the building supervisory authority, you must report the start and completion of certain construction work.

Volltext

The building supervisory authority may require that it be notified of the start and completion of certain construction work. The construction work may only be continued once the building supervisory authority has approved the continuation of the construction work.

General construction supervision is an "optional provision" at the discretion of the building supervisory authority; it is to be exercised irrespective of the duration and intensity of the construction process, the type, size, difficulty and significance of the construction project and the building supervisory procedure.

In addition, construction supervision of the construction of certain building structures is mandatory with regard to the stability and fire protection certificates checked by the building authorities. As part of construction supervision, samples of construction products can also be taken from finished components for testing purposes, if necessary. The building supervisory authority may require that it be notified of the start and completion of certain construction work.

The persons responsible for monitoring must be granted access to properties and facilities, including dwellings, at all times, as well as access to the permits, approvals, test certificates, certificates of conformity, certificates, records of the testing of construction products, construction diaries and other prescribed records.

Erforderliche Unterlagen

  • Building documents
  • Proof of stability
  • Fire protection certificate
  • Building permit
  • Approvals
  • Test certificates
  • Certificates of conformity
  • Certificates
  • Records of the testing of construction products
  • Construction diaries

Voraussetzungen

A building permit must have been granted in accordance with § 63 or 64 or an exemption from approval in accordance with § 62 BremLBO.

Kosten

There are no fees.

Verfahrensablauf

You can display the construction status in paper form.

Paper form

  • You can find the application to print out here in the service portal under "Forms" or on site at the responsible office in paper form.
  • Complete the application.
  • Attach a copy of the required documents to the application.
  • Send everything by post or hand in the documents on site. The completed application should be handed in to the responsible office.
  • You will receive the decision by post.

Bearbeitungsdauer

Not specified.

Frist

The commencement of use must be notified at least two weeks before the commencement of use.

Weiterführende Informationen

nicht vorhanden

Hinweise

Please refer to the building permit to determine whether the notification of certain building conditions is required.